Estimate Points on Requirement used for Parent Feature Remaining Effort should flip to 0 once set to Will not Do

  1. Feature 1 is created in Aha

* Effort = pull from child Requirements

Feature 1 is pushed to ADO

Requirement 1 is created in ADO

* Linked up as a child of Feature 1

* Effort = 3p

* Completed Points = 0p

* Remaining Points = BLANK

Aha is automatically updated and pulls in Requirement 1 under Feature 1 and sets Effort remaining for features = 3p

Requirement 1 is set to Closed/Will not Do in ADO

* Effort = remains 3p

* Completed Points = remains 0p

* Remaining Points = set to 0p

Aha is auto updated to set the Status of the Requirement 1 to Will not do, nothing else happens

* Requirement 1 Estimate still says 3p

* Feature 1 parent of Requirement 1 still showing 3p as the Effort remaining for features

Potential ISSUE:

* Feature 1 parent of Requirement 1 still showing 3p as the Effort remaining for features gives incorrect representation that there is still work to be done when the related Req item was closed our/finaled/placed into the will not do status.