Report on capacity in days

What is the challenge?

We do all of our capacity planning in days, but in Aha I can only report on it in hours in a pivot or list report.

What is the impact?

Capacity feature is basically useless for us.

Describe your idea

We are entering capacity in days. Let us include it in reports in days instead of in hours.

  • Attach files
  • Aha!
    Nathaniel Collum
    Oct 17, 2025

    Hi @Guest - Thanks for sharing this idea.

    In the meantime, I wonder if you have tried using a calculated field.

    Try adding a calculated column with the following formula:

    This will convert the estimate to a whole number in days, but it will initially display it in decimal. You can change that by going to ... > Format column > and selecting "No decimal".

    Now you can use the calculated column in your pivot updates:

    I included both the detailed estimate and the calculated column so you could see them side by side, but you wouldn't need to include both. Hope this helps!