I've created a worksheet on master features that looks at all features in a master feature and presents the min and max dates.
I want the master feature's "Start on" and "Due on" dates to be driven by this worksheet's calculated dates.
image.png
image.png
Open full size
image.png
Guest
May 13, 2025
I have this exact issue, calculating feature dates from custom fields in requirements. Worksheets are a good workaround for missing functionality, and using automations will allow users to better implement those workarounds into the base functionality.
I have this exact issue, calculating feature dates from custom fields in requirements. Worksheets are a good workaround for missing functionality, and using automations will allow users to better implement those workarounds into the base functionality.
Custom formula need to be refreshed within higher levels this is a great opportunity to automate that if a user wants to.